Case Study: Methane Consulting - Sun Valley Industrial Park Sun Valley, CA

Methane Zone Level II | 361,038 SF Footprint

THE CHALLENGE

Sun Valley Industrial Park Building 1 is a large-scale industrial development located within a City of Los Angeles Methane Zone Level II, requiring code – compliant methane mitigation across a 361,038 SF footprint.

The site—pre-leased in part to OnTrac—needed a solution that would meet strict methane mitigation requirements without slowing construction or compromising lease timelines.

With multiple buildings and a tight development schedule, the risk was clear: get the design wrong, and you create delays, added costs, and tenant friction.

SOLUTION

Terra-Petra was engaged by Xebec Building Company to design a comprehensive methane mitigation system across both structures, including:

  • 264,000 SF system for Building 1
  • 96,970 SF system for Building 2

The approach focused on:

  • Full compliance with City of Los Angeles Methane Zone Level II requirements
  • Integration with building design to avoid rework and construction delays
  • Practical, constructible system layouts for large industrial footprints
  • Coordination with project stakeholders to maintain schedule alignment

OUTCOME

The project advanced with a fully compliant, scalable methane mitigation design supporting a major logistics tenant and a high-value industrial asset.

Terra-Petra’s approach enabled:

  • Smooth coordination across a multi-building site
  • Reduced construction friction and risk of redesign
  • Confidence in regulatory compliance without overdesign

Bottom line: a complex methane site was turned into a buildable, leasable industrial asset—without drama.